Nuclear Nuggets Global reactor tracker November edition
Equity Research 11 November 2026 | 6:42AM EST
Nuclear Nuggets: Global reactor tracker - November edition
In the November edition of the Global Reactor Tracker, we highlight the most recent Brian Lee, CFA | developments, data points, and progress across North America, Europe and Asia. Goldman Sachs & Co. LLC
Additionally, we highlight continued resilience/strength in uranium pricing – both in Tyler Bisset, CFA | spot and contract markets – and update our price target for UEC ahead of earnings. Goldman Sachs & Co. LLC
Keshav Choudhary | New reactor progress and announcements Goldman Sachs India SPL
North America 10/15/2026 - Canada - Bruce Unit 4 has completed installation of all 480 calandria tubes as part of its refurbishment, reaching the milestone 25 days faster than Unit 3. Work now moves to fuel channel installation, with the refurbishment expected to add 30–35 years to the reactor’s operating life (here).
10/20/2026 - United States - AtkinsRéalis, Hoosier Energy and the State of Indiana have signed an MoU to explore a nuclear project featuring up to eight Candu reactors with a combined 6 GW capacity. The study will also consider deploying the reactors at retired or retiring power plant sites using a gas-to-nuclear construction model (here).
10/21/2026 - United States - The Nuclear Company has proposed a 6.6 GW nuclear campus in Lewis County, Kentucky, featuring up to six Westinghouse AP1000 reactors, with the initial phase comprising two units. Construction of the Prosperity One project is targeted to begin in 2028 (here).
10/28/2026 - United States - Constellation has secured a conditional loan commitment of up to USD5 billion from the US DOE to support uprates and modernisation across its nuclear fleet in Illinois, Maryland, and Pennsylvania. The planned investments are expected to add nearly 1.1 GW of nuclear capacity (here).
11/3/2026 - Canada - Bruce Unit 5 has been taken offline to begin its Major Component Replacement refurbishment, becoming the fourth unit refurbished under Bruce Power’s six-unit programme (here).
11/9/2026 - Canada - Canada’s 2026 Budget proposes CAD518.5 million over five years to advance nuclear R&D, supply chains, workforce and regulatory capacity under the country’s Nuclear Energy Strategy. Nuclear investments under the strategy have totalled CAD6.5 billion to date, including support for the Darlington New
Goldman Sachs does and seeks to do business with companies covered in its research reports. As a result, investors should be aware that the firm may have a conflict of interest that could affect the objectivity of this report. Investors should consider this report as only a single factor in making their investment decision. For Reg AC certification and other important disclosures, see the Disclosure Appendix, or go to Analysts employed by non-US affiliates are not registered/qualified as research analysts with FINRA in the U.S.
Europe 10/13/2026 - Norway - Norwegian Nuclear Decommissioning has applied to take over the nuclear facilities at Kjeller from the Institute for Energy Technology ahead of their decommissioning. The transfer could take place as early as 1 January 2027, with cleanup of Norway’s Kjeller and Halden sites estimated to cost NOK33–57 billion ($3.6–$6.2 billion) (here).
10/13/2026 - Poland - Poland’s Ministry of Energy, PEJ and PGE have signed an agreement to advance Poland’s second nuclear power plant, with Bełchatów and Konin the preferred locations. A technology partner is targeted for selection in 2027, with construction around 2032 and the first unit starting up around 2040 (here).
10/16/2026 - Slovakia - Mochovce Unit 4 has been connected to Slovakia’s grid and begun supplying electricity, with the 471 MWe VVER-440 operating at 20% power during the initial connection. The unit will undergo staged testing and power increases, culminating in a 144-hour run at 100% power (here).
11/2/2026 - Poland - PEJ has applied for a permit to begin early works for Poland’s first nuclear plant at Lubiatowo-Kopalino, including cooling-water infrastructure, roads and site works ahead of main construction. The three-unit AP1000 project is scheduled to begin construction in 2028, with the first…